Historical Note
- Content Description
- Use of the Collection
- Administrative Information
-
Detailed Description of the Collection
- Organization materials
- Birch Creek Power Company business papers and correspondence
- Federal Energy Regulatory Commission (FERC) information
- Other opposition groups
- Opposition letters
- Photocopies of letters of opposition
- Information in support of the project
- Newspaper articles
- Newsletters, book excerpts and magazine articles
- Reports collected by FOBR
- Environmental and wildlife impacts
- Motions and petitions
- Legal cases
- Binder copy of documents sent to FERC
- Scoping Meeting and Scoping Documents
- Maps
- Miscellaneous
- Names and Subjects
Friends of Bear River records, 1983-1996
Overview of the Collection
- Title
- Friends of Bear River records
- Dates
- 1983-1996 (inclusive)19831996
- Quantity
- 17 boxes, (7 linear feet)
- Collection Number
- UUS_COLL MSS 332
- Summary
- This collection contains the papers of Friends of Bear River and the reports and legal materials they used to present their case against a proposed dam on the Bear River.
- Repository
-
Utah State University, Merrill-Cazier Library, Special Collections and Archives Division
Special Collections & Archives
Merrill-Cazier Library
Utah State University
Logan, UT
84322-3000
Telephone: 4357978248
Fax: 4357972880
scweb@usu.edu - Access Restrictions
-
No restrictions on use, except: not available through interlibrary loan.
- Languages
- English
Historical NoteReturn to Top
In 1989, Birch Creek Power Company owned by Idaho Falls, Idaho engineer Ted Sorenson and Preston, Idaho contractor Robert Fackrell, (S & F Company), proposed to build a dam at the mouth of the Oneida Narrows and subsequently submitted an application to operate a hydroelectric facility to the Federal Energy Regulatory Committee (FERC). The Birch Creek Power Company stated that the benefits of the project would control flooding, generate electricity and store water for downstream use. The project would also offer at least three permanent, full-time positions and thousands of dollars would flow into the community during the 12 to 18-month construction time period. Birch Creek Power Company estimated that the proposed dam would be approximately 100 feet high and would create a reservoir covering 360 acres (117 of those acres were owned by the Bureau of Land Management while the rest were privately owned), and it would approximately cost $112 million to construct. The Preston City Council offered support for the project because of the potential economic benefits it would offer the community. Area residents, however, were more concerned with how the proposed dam and reservoir would impact recreation and wildlife habitat, and in May of 1990, two hundred residents signed a petition opposing the project. In March of 1990, a group of individuals met at a Bureau of Land Management Scoping Hearing and decided to form a group in order to be able to officially present questions at the water rights hearings held by the Idaho Department of Water Resources. This group, the Friends of Bear River (FOBR), collectively represented groups such as The Region Five Wildlife Council, the Bridgerland Audubon Society, Idaho Rivers United, the Idaho Environmental Council, the Eastern Idaho Sierra Club, the Portneuf Valley Audubon Society, the Franklin County Fish and Game Club, and the Utah State University Canoe and Kayak Club. Two key figures in the Friends of Bear River were Currie Lockett who resided in Logan, Utah at the time, and Vicki Smith, who resided on a farm near the proposed site.
On September 28, 1990, Keith Higginson director of the Idaho Department of Water Resources denied Birch Creek Power Company's water right application for the proposed dam due to the overwhelming public opposition, the quantity of water that would be reduced, and the fact that S & F Company lacked sufficient financial resources. In October 1990, S & F Company filed a request for a rehearing for their project but on November 21, 1990, the Idaho Department of Water Resources denied the petition for rehearing due to S & F Company's inability to provide new information and to prove that a new hearing would somehow benefit the public. S & F Company had the option of requesting the district court to review Keith Higginson's decision but declined. However, their application to operate a hydroelectric facility was still pending with FERC and based on a 1990 U. S. Supreme Court ruling, the federal government, not the state, has final authority "to set stream flows at federally licensed dam". FERC thus had the final decision as to whether or not Birch Power Company would be allowed to construct their proposed dam. FERC scheduled two Scoping Meetings, one in Preston, Idaho and the other in Pocatello, Idaho for September 30, 1992 in order to gather public opinion on the project as well as to assess the environmental impacts. On January 20, 1993, it was announced that S & F had withdrawn their application with FERC due to mounting costs. Despite the withdrawal of the application, opponents of the dam continued their efforts. Currie Lockett of Friends of Bear River requested that the state of Idaho study the Bear River in order to designate it as a wild and scenic river in order to protect the area from other future developers. This status, however, was not granted and in 2006 the Twin Lakes Canal Company filed a notice of intent to file a license application with FERC to build a new hydropower facility.
Content DescriptionReturn to Top
This collection contains the papers of Friends of Bear River and the reports and legal materials they used to present their case against a proposed dam on the Bear River. The collection includes Friends of Bear River correspondence as well as photocopies of correspondence between FERC and Birch Creek Power Company obtained by Friends of Bear River, various legal motions, newspaper articles, newsletters, opposition letters, and the scoping documents issued by FERC that outlined the environmental impacts of the proposed dam. In many instances, photocopies were made by Friends of Bear River in order to disperse their materials to multiple people. Items are arranged chronologically when dates are specified. Some portions of the collection have been maintained in their original order, such as letters of opposition in Box 6 folders 1-20.
Use of the CollectionReturn to Top
Restrictions on Use
It is the responsibility of the researcher to obtain any necessary copyright clearances.
Permission to publish material from the Friends of Bear River Collection must be obtained from the Special Collections Manuscript Curator and/or the Special Collections Department Head. and/or the Special Collections and Archives department head.
Preferred Citation
Initial Citation: Friends of Bear River records USU_COLL MSS 332, Box [ ]. Special Collections and Archives. Utah State University Merrill-Cazier Library. Logan, Utah.
Following Citations: USU_COLL MSS 332, USUSCA.
Administrative InformationReturn to Top
Arrangement
Arranged chronologically when dates are specified.
Processing Note
Processed in October of 2007.
Acquisition Information
The materials in this collection consisted of four boxes that were donated to USU Special Collections and Archives by Dan Miller on April 4, 2006.
Bibliography
Herald Journal February 25, 1990 Herald Journal , May 23, 1990 Herald Journal , May 24, 1990 Herald Journal , September 30, 1990 Herald Journal , November 21, 1990 Herald Journal , April 25, 1991 Preston Citizen , January 20, 1993Detailed Description of the CollectionReturn to Top
Organization materials, 1990-1996Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
1 | 1 | Friends of Bear River background information |
undated |
1 | 2 | Friends of Bear River attorney search |
1990 August 1-20 |
1 | 3 | Friends of Bear River sign-up sheet to help |
undated |
1 | 4 | Questionnaire |
undated |
1 | 5 | Notes to Friends of Bear River supporters |
undated |
1 | 6 | Sign-up sheet for site visit |
1992 September 29 |
1 | 7 | List of organizations |
1990 October 4 |
1 | 8 | Active List and organization list |
undated |
1 | 9 | Mailing addresses |
undated |
1 | 10 | Mailing addresses continued |
undated |
1 | 11 | Co-Interveners and Co-Signers addresses |
undated |
1 | 12 | Addresses of recipients Section 6.0 |
undated |
1 | 13 | Political Addresses |
undated |
1 | 14 | Idaho Fish & Game Commissioners addresses |
undated |
1 | 15 | Idaho Water Resources Board addresses |
undated |
1 | 16 | Correspondence from State of Idaho Department of Water Resources |
1990 July 24 - 1990 September 10 |
1 | 17 | Correspondence from Congressman Richard Stallings |
1990 October 29 - 1990 November 13 |
1 | 18 | Incoming correspondence |
1990 July 19 - 1993 May 24 |
1 | 19 | Outgoing correspondence |
1990 January 20 - 1990 September 27 |
1 | 20 | Outgoing correspondence |
1991 January 21 - 1996 July 10 |
1 | 21 | Pending letters |
undated |
1 | 22 | Pending letters (continued) |
undated |
1 | 23 | Friends of Bear River miscellaneous notes |
undated |
Birch Creek Power Company business papers and correspondence, 1989-1992Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
2 | 1 | Construction Cost Estimate |
undated |
2 | 2 | Average Cost Rates |
undated |
2 | 3 | Sorensen Engineering license application list of deficiencies from FERC |
1989 March 31 |
2 | 4 | Schedule A from FERC to Sorensen Engineering requesting additional information |
1989 December 7 |
2 | 5 | Schedule A from FERC to Sorensen Engineering requesting additional information |
1990 August 13 |
2 | 6 | Sorensen Engineering Appendix A: Consultations |
1990 August 20 - 1990 October 11 |
2 | 7 | Photocopies of correspondence between Sorensen Engineering and FERC |
1986 February 6 - 1989 December 14 |
2 | 8 | Photocopies of correspondence between Sorensen Engineering and FERC |
1990 March 6 - 1990 December 13 |
2 | 9 | Photocopies of correspondence between Sorensen Engineering and FERC |
1991 January 29 - 1991 May 22 |
2 | 10 | Photocopies of letters from U.S. Department of Interior to Sorensen Engineering |
1989 January 3 - 1991 January 15 |
2 | 11 | Photocopy of letter from Sorenson Engineering to Idaho Department of Fish and Game regarding agreement to provide mitigation for exceptional benefits exemption |
1990 September 18 |
2 | 12 | Photocopies of correspondence between FERC and Fackrell Construction |
1990 July 10 - 1992 October 27 |
2 | 13 | Photocopy of letter from State of Utah Department of Natural Resources Division of Water Resources to Sorensen Engineering |
1991 March 12 |
2 | 14 | Miscellaneous photocopies of Sorensen Engineering outgoing letters |
1989 May 3 - 1990 December 13 |
Federal Energy Regulatory Commission (FERC) information, 1985-1992Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
3 | 1 | Photocopies of correspondence from U. S. Department of Interior to FERC |
1985 December 23 - 1990 June 29 |
3 | 2 | Memo to FERC from Geoffrey Hogander, wildlife biologist |
1989 January 3 |
3 | 3 | Letter from FERC to Governor Cecil Andrus |
1990 January |
3 | 4 | Photocopies of correspondence from Pacific Water and Power, Inc to FERC |
1989 September 30 - 1991 March 1 |
3 | 5 | Miscellaneous photocopies of correspondence from various agencies to FERC |
1985 October 29 - 1992 October 22 |
3 | 6 | FERC Document Tracking List |
undated |
3 | 7 | Active FERC projects in Idaho |
1992 March 4 |
3 | 8 | FERC outgoing correspondence |
1992 August - October |
Other opposition groups, 1996Return to Top
arranged alphabetically
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
4 | 1 | American Rivers |
undated |
4 | 2 | Audubon Society |
undated |
4 | 3 | Friends of Fall River correspondence |
undated |
4 | 4 | Idaho Rivers United |
undated |
4 | 5 | Idaho Rivers United (continued) |
undated |
4 | 6 | Land and Water Fund |
undated |
4 | 7 | Oneida 5 Dead or Alive poster |
undated |
4 | 8 | People for Wise Water Planning |
undated |
4 | 9 | River Network |
undated |
4 | 10 | Save Our Streams Volunteer Water Monitoring Survey |
undated |
4 | 11 | Sierra Club |
undated |
4 | 12 | The Snake River Alliance |
undated |
4 | 13 | Trout Unlimited |
undated |
4 | 14 | Opposition flyers and brochures |
undated |
4 | 15 | Signed petitions |
undated |
4 | 16 | Friends of Bear River Response to Pacificorp First Stage Consultation for Oneida Hydroelectric Project Relicensing |
undated |
4 | 17 | Opposition group comments on First Stage Consultation Documents for the Soda, Grace/Cove, and Oneida hydroelectric projects |
1996 July 11 |
Opposition letters, 1992Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
5 | 1 | Photocopies of letters of opposition sent to FERC |
1990 September 22 - 1992 October 26 |
5 | 2 | Photocopies of letters of opposition sent to FERC |
1992 October 27 - November 18 |
5 | 3 | Record of Public Issues 1-20 |
undated |
5 | 4 | Record of Public Issues 21-40 |
undated |
5 | 5 | Record of Public Issues 41-60 |
undated |
5 | 6 | Record of Public Issues 61-80 |
undated |
5 | 7 | Record of Public Issues 81-100 |
undated |
5 | 8 | Record of Public Issues 101-115 |
undated |
5 | 9 | Record of Public Issues 116-124 |
undated |
5 | 10 | Additional public issues |
undated |
Photocopies of letters of opposition, 1990-1992Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
6 | 1 | Newspaper Letters to the Editor |
undated |
6 | 2 | Letters pointing out beauty created by God |
undated |
6 | 3 | Letters pointing out dam effects at Mink Creek. Includes four colored photographs of Mink Creek |
undated |
6 | 4 | Letters regarding dam safety |
undated |
6 | 5 | Letters of opposition regarding areas of critical environmental concerns |
undated |
6 | 6 | Letters of opposition concerning fish and game |
undated |
6 | 7 | Letters concerned about fossil beds |
undated |
6 | 8 | Letters of opposition to preserve history |
undated |
6 | 9 | Letters of opposition from hunters |
undated |
6 | 10 | Letters concerned about possible law suits |
undated |
6 | 11 | Letters of opposition in regards to money for a few |
undated |
6 | 12 | Letters concerned with nitrification |
undated |
6 | 13 | Letters regarding public access |
undated |
6 | 14 | Letters concerned about the impact for recreational use |
undated |
6 | 15 | Letters regarding road access |
undated |
6 | 16 | Letters concerned about the impact on rock squirrels |
undated |
6 | 17 | Letters from residents of Utah |
undated |
6 | 18 | Letters of opposition concerning wetlands below project |
undated |
6 | 19 | Letters of opposition stating the project is not worth it |
undated |
6 | 20 | Miscellaneous opposition letters |
1990 May 5 - June 15 |
6 | 21 | Miscellaneous opposition letters |
1990 June 17 - August 29 |
6 | 22 | U. S. Department of the Interior Visitor's Rosters from Preston, Idaho and Pocatello, Idaho |
1990 May 22 |
6 | 23 | Letter from Idaho Governor Cecil Andrus to Senate and House Energy Committee Chairmen |
1992 September 22 |
6 | 24 | Unsigned letter to Congressmen Richard H. Stallings |
1992 September 30 |
Information in support of the project, 1990-1992Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
7 | 1 | School Finance |
undated |
7 | 2 | Western Area Power Administration mailing |
undated |
7 | 3 | Letters expressing support |
1988 August 5 - 1990 August 29 |
7 | 4 | Letters expressing support |
1992 October 27 |
Newspaper articles, 1990-1994Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
8 | 1 | Newspaper articles |
1987 July 17 - 1990 May 27 |
8 | 2 | Newspaper articles |
1990 June 5 - December 21 |
8 | 3 | Newspaper articles |
1991 January 17 - October 9 |
8 | 4 | Newspaper articles |
1992 April 1 - November 24 |
8 | 5 | Newspaper articles |
1993 January 10 - November 10 |
8 | 6 | Newspaper articles |
1994 June 16 - August 25 |
8 | 7 | Newspaper articles |
undated |
8 | 8 | News release by Idaho Department of Water Resources announcing public hearing on Oneida Narrows Water Right |
1990 July 25 |
8 | 9 | Newspaper articles on contractor and engineer competency |
1990 October 10 - 1992 June 24 |
8 | 10 | Newspaper articles on contractor and engineer competency |
1992 July 12 - September 21 |
8 | 11 | Photocopies of newspaper articles regarding engineering issues on other dams |
1992 June 25 - September 21 |
8 | 12 | Photocopies of newspaper articles on Utah water usage from Salt Lake Tribune |
undated |
Newsletters, book excerpts and magazine articles, 1988-1993Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
9 | 1 |
The Murrelet , Vol. 69, No. 2 |
1988 Summer |
9 | 2 |
High Country News , Vol. 23, No. 14 |
1991 August 12 |
9 | 3 |
Southern Utah Wilderness Alliance Vol. VIII, No. 3 |
1991 Fall |
9 | 4 |
Little Bear Newsletter No. 2; No. 1 |
1991 September - 1993 July |
9 | 5 |
WALU Sentinel newsletter Vol. 3, No. 3 |
1992 March |
9 | 6 |
Recycling Times newsletter, Vol. 3, No. 1 |
1992 Spring |
9 | 7 |
High Country News article, "The Electric Revolution" pages 6-14, 23, 26-28 |
1992 June 29 |
9 | 8 |
Utility Environment Report article titled, U.S. Generating: Early Environmental Analysis is Key to Power Contracts" |
1992 October 16 |
9 | 9 |
Northwest Power Planning Council newsletters Vol. 9, No. 12 and Vol. 10, No. 1 |
1992 December - 1993 January |
9 | 10 |
Utah Watershed Review Focus: "The Bear River", Vol. 1, No. 3 |
1993 May-June |
9 | 11 | COOP America Quarterly magazine |
1993 Spring |
9 | 12 |
Northwest Energy News newsletter by Northwest Power Planning Council, Vol. 12 No. 5 |
1993 September-October |
9 | 13 |
Basin, Range and Rimrock newsletter |
1993 Fall |
9 | 14 |
The Volunteer Monitor Vol. 6, No. 1 |
1994 Spring |
9 | 15 | Article by Warren Cornwall titled, "Idaho Rivers vs. Idaho Dams"
Accompanying letter states that it was to be printed in High Country News later that winter.
|
1990 July |
9 | 16 | Photocopied pages from Environmental Economics , by Joseph Seneca and Michael K. Taussig, 3rd Ed. Pages 287-288, 312-319 |
undated |
9 | 17 | Photocopied pages from Natural Resource Damages: Law and Economics by Kevin Ward and John Duffield. Pages 527-554 |
undated |
9 | 18 | Article titled, "The Water Profiteers", by Peter Steinhart |
undated |
9 | 19 | Article titled, "It's Wake-up Time for Main Street when Wal-Mart Comes to Town", by Donald Dale Jackson |
undated |
Reports collected by FOBR, 1984-1994Return to Top
arranged chronologically
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
10 | 1 | Idaho Geological Survey report |
1984 July |
10 | 2 | Idaho Geological Survey report |
1984 November |
10 | 3 | U. S. Department of Interior Report on Owyhee River management plan |
1985 |
10 | 4 | Idaho State Water Plan report by Water Resources Board |
1989 December 12 |
10 | 5 | Northwest Power Planning Council (NWPPC) Protected Areas report |
1987 October 8 |
10 | 6 | Supporting Design report for Sorensen Engineering |
1988 November |
10 | 7 | White Horse Associates' investigation on vegetation and soil in Oneida Narrows |
1989 January |
10 | 8 | FERC licensing status report of Idaho hydropower projects |
1989 March 31 |
10 | 9 | Preliminary and Supplementary Geological report for Sorensen Engineering |
1989 June |
10 | 10 | Division of Water Resources memo on seismotectonic setting |
1990 February 12 |
10 | 11 | Northwest Power Planning Council (NWPPC) report titled, "New Resources: Supply Curves and Environmental Effects" |
1990 February 28 |
10 | 12 | Idaho State University statement regarding geologic hazards |
1990 August 16 |
10 | 13 | Report and corresponding letter from Idaho Department of Water Resources on proposed project |
1990 August 21 |
10 | 14 | Northwest Power Planning Council (NWPPC) list of project-related changes, report 90-10 |
1990 August 22 |
10 | 15 | Bear River Pre-Design Study by Division of Water Resources |
1990 October 15 |
10 | 16 | Integrated Resource Plan |
1990 - 1992 |
10 | 17 | Report and order on standards and guidelines for Integrated Resource Plan |
1992 June 18 |
10 | 18 | Idaho Water Resources Board's Comprehensive State Water Plan |
1992 |
10 | 19 | Franklin Soil and Water Conservation District Annual Report |
1992 |
10 | 20 | U.S. Department of Interior mailing list of structural projects in Idaho |
1994 |
10 | 21 | Water Quality Status Report on Bear River by Idaho Department of Health and Welfare |
undated |
10 | 22 | Partial report by geologist Robert Bright |
undated |
Environmental and wildlife impacts, 1985-1992Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
11 | 1 | New access road proposed by Fackrell and its impacts |
undated |
11 | 2 | Access to Bear River |
undated |
11 | 3 | Counts and activities in Bear River Canyon |
1990 Summer |
11 | 4 | Traffic counts that includes colored photos |
undated |
11 | 5 | FERC Environmental Impact Statement |
1992 February |
11 | 6 | Economic feasibility |
undated |
11 | 7 | Idaho Fish and Game Concerns on Bear River Narrows Project |
undated |
11 | 8 | Impact on Canadian geese and marshes |
undated |
11 | 9 | Geological Impacts |
undated |
11 | 10 | Raptor impacts that includes photos of perched eagles |
undated |
11 | 11 | Colored photos of soil sloughing off of river liner |
undated |
11 | 12 | Water conservancy district brochures |
undated |
11 | 13 | Cumulative Impacts |
undated |
11 | 14 | FOBR outline of consequences of denial |
undated |
11 | 15 | FOBR Alternative Proposal |
undated |
11 | 16 | FOBR No Action Alternative |
undated |
11 | 17 | Proposed Research Natural Areas |
1985 August 16 |
Motions and petitions, 1985-1993Return to Top
arranged chronologically
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
12 | 1 | Administrative Procedure 67-5210 |
undated |
12 | 2 | FERC Formal Requirements for Filings in Proceedings Before the Commission |
undated |
12 | 3 | Idaho Supreme Court Case Edward C Shokal, Cole M. Reed and State of Idaho, Department of Fish and Game Billie Reed vs. A. Kenneth Dunn, Director, Department of Water Resources and Trout Co. |
1985 September 24 |
12 | 4 | FERC Notice of Intent Of Utah Board of Water Resources to file Competing Preliminary Permit Application filed by Birch Power Company, Inc. |
1985 December 2 |
12 | 5 | Utah Board of Water Resources Notice of Withdrawl of Its Notice of Intent |
1986 January 2 |
12 | 6 | FERC Order Issuing Preliminary Permit issued to Birch Power Company, Inc. |
1986 January 16 |
12 | 7 | Notice of Changes to Bear River FERC Application |
1989 January |
12 | 8 | Application for License For Major Unconstructed Project prepared by Sorensen Engineering, P.A. to FERC |
1989 January 12 |
12 | 9 | Information meeting minutes held in Preston, Idaho, March 20, 1989 and attached resolution |
1989 May 12 |
12 | 10 | Notice of Application Filed with the Commission by Birch Power Company, Inc. for application for major license filed on January 13, 1989. |
1989 August 21 |
12 | 11 | Motion to Intervene and Petition to Deny Application For A Major License submitted to FERC by The State of Idaho in regards to a major license application filed by Birch Power Company. |
1989 October 26 |
12 | 12 | FERC Notice Granting Late Intervention to Idaho Department of Fish and Game to intervene in Birch Power Company, Inc.'s application. |
1989 December 7 |
12 | 13 | Amended Motion to Intervene submitted to FERC by The State of Idaho on a motion that was filed on October 30, 1989 by Birch Power Co. |
1990 January 8 |
12 | 14 | Resolution on the matter of the effect the Bear River Narrows Hydro electric project on the Oneida Narrows reservoir site identified as a protected reservoir site in the state water plan. Passed and approved |
1990 February 23 |
12 | 15 | Motion to Intervene and Petition to Deny Application submitted to FERC by The State of Idaho for a permit application filed by Hydro-Power of Nevada. |
1990 March 28 |
12 | 16 | Department of Water Resources of the State of Idaho Notice of Hearing in the matter of an application by S & F Power Company to appropriate the public waters of the State of Idaho. |
1990 April 25 |
12 | 17 | Petition filed by FOBR for Leave to Intervene Before the Idaho Department of Water Resources |
1990 July 13 |
12 | 18 | Denied order to petition filed by Currie Locket to intervene as a full party |
1990 August 16 |
12 | 19 | Petition filed by FOBR for Rehearing Application to Appropriate Water |
1990 August 30 |
12 | 20 | Petition filed by FOBR to Deny Application to Appropriate Water |
1990 August 30 |
12 | 21 | FOBR Petition to Deny Application to Appropriate Water Before the Idaho Department of Water Resources Regarding Bear River Narrows Project No 9215. |
1990 August 30 |
12 | 22 | FOBR Submission of Evidence and Arguments |
1990 August 30 |
12 | 23 | Friends of Bear River Petition to Withdraw Exemption to the Northwest Power Planning Council.
(two copies)
|
1990 September 5 |
12 | 24 | Petition for Rehearing filed by S & F Power Co. to appropriate water of the Bear River for power purposes |
1990 October 17 |
12 | 25 | Notice Granting Late Intervention filed by FOBR to FERC to intervene in the Birch Power Co. license application that was filed on January 17, 1991. |
June 21, 1991 |
12 | 26 | Moratorium Order In the Matter of Applications and Permits for the Diversion and Use Water Within the Salmon and Clearwater River Basins, Idaho by The State of Idaho Before the Department of Water Resources. |
1992 May 15 |
12 | 27 | Moratorium Order In the Matter of Applications For Permit For Diversion and Use of Ground Water Within the Bear River Drainage and Great Basin Tributaries by The State of Idaho Before the Department of Water Resources. |
1992 May 15 |
12 | 28 | Moratorium Order In the Matter of Application for Permits for Diversion and Use of Surface and Ground Water Within the Snake River Basin Upstream from the USGS Gauge on the Snake River near Weiser by The State of Idaho Before the Department of Water Resources. |
1992 May 15 |
12 | 29 | Motion to Intervene filed by American Whitewater Affiliation and American Rivers, Inc. with FERC against Utah Power and Light Company in regards to the Cutler project |
1992 August 17 |
12 | 30 | Notice of application for license for the construction of the Bear River Narrows hydropower project |
1992 September. 9 |
12 | 31 | Petition filed by Friends of Bear River to Continue Agency and Public Scoping Hearings and To Extend Filing Deadline
Also includes a handwritten message from Currie Lockett to FOBR attorney Brad Wright on content of petition.
|
September 23, 1992 |
12 | 32 | Final order from Idaho Water Resources Board in the matter of a permit to establish a minimum lake level on Bear Lake |
1993 November 15 |
Legal cases, 1983-1993Return to Top
arranged chronologically
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
13 | 1 | Idaho Water Law Handbook |
1983 October |
13 | 2 | Supreme Court of Idaho Kootenai Environ. Alliance v. Panhandle Yacht v. State Board of Land Commissioners and Dept. of Lands, Cross-Respondents |
1983 November 2 |
13 | 3 | Protected Areas Rule adopted |
1988 August 10 |
13 | 4 | U. S. Supreme Court case California v Federal Energy Regulatory Commission Et. Al. decision |
1990 May 21 |
13 | 5 | District Court of the Fourth Judicial District Earl M. Hardy v. R. Keith Higginson, Director, Idaho Department of Water Resources |
1990 July 25 |
13 | 6 | H. R. 649 to amend the Federal Power Act in the 102D Congress 1st Session |
1991 |
13 | 7 | Idaho Docket |
1992 December |
13 | 8 | Idaho Boating Laws and Rules updated |
1993 July 1 |
13 | 9 | Article from Idaho Law Review titled "The Role of States and Federal Agencies in Conditioning FERC Licenses", by Scott W. Reed |
undated |
13 | 10 | Idaho State Water Laws 42-402, 42-203 and 42-203A |
undated |
13 | 11 | General Information for Nominating a River for Wild and Scenic Status |
undated |
Binder copy of documents sent to FERC, 1990Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
14 | 1 | Binder submitted to FERC to intervene in opposition to the application for a major license submitted by Birch Power Co. |
1990 December 19 |
14 | 2 | Motion to Intervene in opposition to the Application for a major license filed by FOBR |
1990 December 19 |
14 | 3 | Appendices to motion to intervene in opposition Exhibits A-1 & A-2 (match with Box 12) |
undated |
14 | 4 | Appendix B: Recreation |
undated |
14 | 5 | Additional information on Recreation |
undated |
14 | 6 | Appendix C: Fishery Loss |
undated |
14 | 7 | Appendix D: Wildlife and Habitat Loss |
undated |
14 | 8 | Additional information on fish and wildlife |
undated |
14 | 9 | Appendix E: Environment and Water Quality |
undated |
14 | 10 | Additional information on water quality. Conference brochure |
1990 September 22-23 |
14 | 11 | Appendix F: Geology and Dam Safety |
undated |
14 | 12 | Appendix G: Other Consequences |
undated |
14 | 13 | Additional information on other consequences |
undated |
14 | 14 | Appendix H: Flow and Reservoir Level |
undated |
14 | 15 | Additional information on flow and reservoir level |
undated |
14 | 16 | Appendix I: Economic Feasibility |
undated |
14 | 17 | Additional information on economic feasibility |
undated |
14 | 18 | Appendix J: Power Not Needed |
undated |
14 | 19 | Additional information on power not needed |
undated |
14 | 20 | Appendix K: Conflicts with Agency Plans |
undated |
14 | 21 | Appendix L: Public Opposition |
undated |
14 | 22 | Additional information on public opposition |
undated |
Scoping Meeting and Scoping Documents, 1992Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
15 | 1 | FERC Scoping Document 1 for Bear River Narrows Project |
1992 September 18 |
15 | 2 | Memo announcing scoping meetings and objectives from FERC |
1992 September 18 |
15 | 3 | FERC Public Scoping Meeting stenographers report, Preston, Idaho |
1992 September 30 |
15 | 4 | FERC Public Scoping Meeting stenographers report, Pocatello, Idaho |
1992 September 30 |
15 | 5 | Scoping meeting attendees |
1992 September 30 |
15 | 6 | Idaho Department of Fish and Game scoping comments |
1992 October 26 |
15 | 7 | Birch Power Company scoping comments |
1992 October 29 |
15 | 8 | Bureau of Land Management (BLM) formal review comments on Scoping Document 1 |
1992 October 29 |
15 | 9 | EPA comments on scoping documents |
1992 October 30 |
15 | 10 | Idaho Department of Parks and Recreation scoping comments |
1992 October 30 |
15 | 11 | Supplement to oral comments at public scoping hearing from FERC to FOBR |
1992 October 30 |
15 | 12 | Department of Fisheries and Wildlife recommendations to Scoping Document 1 |
1992 November 25 |
15 | 13 | FERC Scoping Document 2 |
1992 December 4 |
Maps, 1990Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
16 | 1 | Hand-drawn maps that includes seven colored photographs of area |
undated |
16 | 2 | Oneida Project Maps |
undated |
16 | 3 | Division of Water Resources Mapping Update |
1990 March 20 |
16 | 4 | Maps of Utah, Idaho, and Wyoming |
undated |
16 | 5 | Maps of Utah, Idaho, and Wyoming (continued) |
undated |
16 | 6 | Bear River Narrows Hydroelectric Project Map |
undated |
16 | 7 | Bear River Project Reservoir Map compared to Glendale Reservoir Map |
undated |
16 | 8 | Aerial photo showing property lines around Bear River |
undated |
Miscellaneous, 1991-1994Return to Top
Container(s) | Description | Dates | |
---|---|---|---|
Box | Folder | ||
17 | 1 | Western Governors' Association Conference |
1991 October 10-12 |
17 | 2 | Rocky Mountain Environmental Directory response form |
1992-1993 |
17 | 3 | National Water Policy Roundtable Conference |
1992 |
17 | 4 | Western Systems Coordinating Council as suggested reading |
1992 April |
17 | 5 | Western Water Conference Agenda |
1994 August 13-14 |
17 | 6 | Black and white photocopies of photographs of Oneida Reservoir and Borrow Pit area |
undated |
17 | 7 | Five colored photographs of unspecified area showing gravel road and four colored photographs showing patterns in the dirt. Also includes three colored photographs of unknown individuals and a colored photograph of cucumber plants. Includes negatives. |
undated |
17 | 8 | Excerpts from a Task Force meeting minutes |
undated |
17 | 9 | Whitewater safety guidelines from American Red Cross |
undated |
Names and SubjectsReturn to Top
Subject Terms
- Dams--Bear River (Utah-Idaho)
Geographical Names
- Bear River (Utah-Idaho)
- Bear River (Utah-Idaho)--Power utilization.